MARJAN INCREMENT PROGRAM SINOPEC

The project involves the construction of site facilities on a 45,500 m2 land for Sinopec and Saudi Aramco. The scope of work includes site preparation, fence and gates, asphalt, and walkways, construction of 5,500 m2 office buildings for Saudi Aramco and Sinopec team with furniture and HVAC, and complete utilities such as water networks, firefighting networks, power networks, fire alarm system, piping, tanks, cables, lighting, generators, pumps, and others. In addition, 2,000 m2 steel structure warehouses will be constructed with site preparation, fence and gates, asphalt and walkways, furniture, and HVAC, along with complete utilities.

Project Information
Project Location:
Tanajib, KSA
Start Date:
December 2019
Completion Date:
August 2020