HARAD GAS PLANT: CONSTRUCTION OF TR SATELLITE OFFICES
Construction of satellite offices for Tecnicas Reunidas and Saudi Aramco, covering a total area of 12,000 m2 in 17 different Locations. The project included site preparation, installation of fences and gates, walkways and furniture, and HVAC systems. The offices were equipped with complete utility systems, including water networks, firefighting networks, power networks, fire alarm systems, piping, tanks, cables, lighting, generators, pumps and other necessary equipment. In addition, the offices were equipped with recreational and dining facilities, a gymnasium and sports facilities, making it a complete turn-key project.
Project Information
Clients:
TECNICAS REUNIDAS SAUDI ARAMCO
Project Location:
Harad, KSA
Start Date:
May 2018
Completion Date: